By ROD AMNER

A Facebook post by Democratic Alliance (DA) Ward 4 councillor Geoff Embling has reignited long-standing grievances about the closure of Jamieson and Milner dams to the public.

The dams and surrounding area are on municipally-owned commonage and were for decades a beloved recreational spot for Makhandans.

However, the gate to the area has been locked with a thick cable since 2017. A sign prohibiting entrance and recreational activity of any kind was also erected at the time.

One of two signs erected at Jamieson Dam in 2017. Photo: Rod Amner

In 2020/2021, Public Service Accountability Monitor (PSAM) director Jay Kruuse and the Makana Residents Association’s (MRA) Tim Bull prepared a detailed proposal to senior Makana Municipality managers to manage public recreational access to the area.

Tim Bull
Jay Kruuse

In his response letter to Kruuse and Bull dated 22 April 2021, Makana Municipal Manager Moppo Mene said, “Residents can be allowed to walk, run, and walk their dogs and other domesticated animals in the area.”

“What is not allowed is:

  • Farming and allowance of stock in the area;
  • Hunting;
  • Fire;
  • Parties.”

Mene said the sign prohibiting entrance and recreational activity of any kind would be “revised accordingly in the near future”.

Makana Municipal Manager Moppo Mene

But, the old signboard is still up. And the gate was still locked when Grocott’s Mail visited the site on Thursday, 3 February.

In their submission to the Municipality, Kruuse and Bull suggested that a new sign be erected with the following information:

  • Use of the area is entirely at visitors own risk and that MLM cannot be held liable for any damage, injury or loss sustained (preferably in both IsiXhosa and English);
  • The making of fires, the hunting of animals, littering and causing of damage to or removal of fauna and flora is strictly prohibited;
  • No members of the public may tamper with any municipal equipment situated at or near the dams;
  • A telephone number and email address can be used to report any allegations of abuse of this area to the Municipality.

Kruuse and Bull further encouraged the municipality to “display similar signs at Grey Dam, Dog Dam, Settlers Dam, Howieson’s Poort Dam (and any others) to ensure consistency of messaging to the public”.

Another concern raised by residents on Facebook is the continued presence of cattle, pigs and goats in the area.

In 2017, Makana Parks Manager Jeff Budaza told Grocott’s’ Mail that one of his staff had facilitated the lease of the land and the dam by some Grahamstown families for stock grazing.

In their submission to the Municipality, Kruuse and Bull noted the significant health risks that livestock poses to these drinking water source assets of the Municipality.

In his response to Kruuse and Bull, Municipal Manager Mene made it clear that stock farming would not be allowed in the area.

A recent photo of cattle grazing at Jamieson Dam taken by Democratic Alliance (DA) Ward 4 councillor Geoff Embling.

Dam upgrades

In January 2020, work commenced on repairs to the dams, funded by a Department of Water and Sanitation (DWS) Water Services Infrastructure Grant (WSIG). ZKS Projects was appointed as the contractor, and MBB Consulting Engineers supervised the project.

MBB managing director Pravesh Nosib said a great deal was accomplished in Phase 1 of the project, which ended in January 2021 (see below for a full report and photos of what was achieved).

ZKS Projects managing director Zukile Bota said both dams were operational. Water from the dams, built at the turn of the 20th century, is currently being distributed to local farms.

Over the years, residents expressed concern about a rusted valve on the water tower in Jamieson’s dam, which allowed water to escape to the lower-lying Milner dam. However, a new outlet valve was installed on the other side of the dam wall embankment as part of the upgrades to the facility in 2020/2021. According to Bota, no water is leaking from either the Jamieson or Milner dams.

The rusted water tower at Jamieson Dam. Water used to leak through an open valve on the tower, but overflow is now controlled by new valves installed behind the embankment. Photo: Rod Amner
The new concrete overflow valves installed at the back of the embankment. Photo: Rod Amner

The ladder to the dangerously rusted catwalk that links the water tower to the embankment was removed by ZKS Projects for safety reasons.

The contractors decided to remove the first half of the rusty water tower bridge at both dams to prevent easy access to the tower head. Photo: Rod Amner

What else was achieved in Phase 1 of the upgrade to the dams?

According to MBB Consulting Engineers, who supervised the upgrade project, the most immediate issues identified and attended to as part of the planned repairs to the dams were:

  • Removal of vegetation growth on the embankments. Once vegetation was removed, damage to the riprap was repaired and tree growth was eliminated.
  • Repairs to spillways and the return channels were undertaken by constructing a concrete overflow structure to prevent further erosion to the spillway.
  • Replacement of the stolen supply lines. Cast iron had been used as the original water main linking the two dams and a substantial section of the cast iron had been exposed, smashed, and carried off to scrap metal dealers.
  • Replacement of the downstream valve gear, scour valves, and meters.
  • Installation of gauge plates and the fitment of telemetry linking to the existing municipal SCADA system.
  • Construction of service roads on top of embankments.

In addition, the contractors were charged with finding and repairing leaks. This was investigated, and the following repairs were made:

  • Water leaks along the gravity main: several kilometres of leaking pipes downstream from the Milner dam were reported and repaired. One break on a low-lying farm drained the Milner dam of its last 5% of water storage overnight.
  • A section of cast iron water main, installed at a shallow depth, was cracked when traversed by a bulldozer and required immediate repair.
  • An additional ± 230m of exposed and unretained water main piping was replaced with uPVC in an area that was solid bedrock. The uPVC pipe was retained by concrete anchor blocks dowelled into the existing bedrock.

Jamieson Dam’s recreational paradise. Photo: Rod Amner
This is the current level of the Jamieson Dam. A rather dismal 70cm. Photo: Rod Amner
This is where the level should ideally be. Photo: Rod Amner
It is hoped this sign will be replaced with something more in synch with Makana’s tagline soon. Photo: Rod Amner

Comments are closed.